Planning & Investment Knowledge Base

Work category 451: Walking facilities

 

Introduction

This work category A type of activity – not confined to a particular activity class, e.g. new roads (work category 323) appears in:

* activity class 12 – local road improvements
* activity class 13 – state highways improvements
provides for the construction/implementation of new or improved walking facilities.

 

This definition applies to the 2012-15 NLTP A National Land Transport Programme Interrelated and complementary combination of activities that, when delivered in a coordinated manner, produce synergies – can span more than one work category and more than one activity class, e.g. a programme could include a road improvement and public transport improvement activities. adopted by the NZTA under section 19 of the LTMA, as from time to time amended or varied .  For the 2015-18 NLTP please refer to the updated definition for work category 451.

 

Examples of qualifying activities

Examples include, but may not be limited to:

  • new or improved footpaths That portion of the road reserve set aside for the use of pedestrians only. , including on an existing bridge
  • pedestrian crossing A specially marked area giving right of way to pedestrians crossing the road. features, including kerb A border of rigid material, usually raised, which is formed at the edge of a traffic lane or shoulder. crossings, kerb protrusions, central refuges and pedestrian platforms
  • pedestrian crossing A specially marked area giving right of way to pedestrians crossing the road. controls, including zebra crossings, kea crossings and pedestrian traffic signals
  • signage
  • altering kerb A border of rigid material, usually raised, which is formed at the edge of a traffic lane or shoulder. lines to improve pedestrian access
  • pedestrian shelters (excluding shelters that are primarily provided for waiting for, or getting to or from, passenger transport)
  • pedestrian overbridges/underpasses A grade separation where the traffic passes under an intersecting highway or railway.
  • pedestrian crossings of railways, and
  • all markings, traffic signals, lighting, etc necessary to bring the facility into service.

 

Other potential activities that are not in the above list should be discussed with NZTA for eligibility.

 

Exclusions

Walking facilities used purely for recreational purposes are not eligible.

 

To retain consistency shared walking and cycling facilities should be included in work category 452: Cycle facilities.

 

Funding assistance rate

The usual funding assistance rate is:

  • the Approved Organisation’s construction rate
  • 100 percent for the NZTA (state highways).
 
 

Last Updated: 01/09/2020 1:25pm