Introduction |
This page relates to the 2012-15 NLTP A National Land Transport Programme Interrelated and complementary combination of activities that, when delivered in a coordinated manner, produce synergies – can span more than one work category and more than one activity class, e.g. a programme could include a road improvement and public transport improvement activities. adopted by the NZTA under section 19 of the LTMA, as from time to time amended or varied only.
For the latest information, please see the Assessment Framework for the 2015-18 NLTP.
This section provides guidance on incremental assessment to assist option selection, optimise packages and evaluate proposed scope changes. |
What is incremental assessment? |
Incremental assessment involves the evaluation of differences in effectiveness and efficiency amongst mutually exclusive investment options, including proposed changes in scope to endorsed macroscopes. The incremental assessment informs the investment decision, e.g. which option should be selected as the preferred option? |
Considers full assessment profile The three-part rating for an activity, rated as high, medium or low e.g. HMM, and representing the assessment for Strategic Fit, Effectiveness, and Benefit and Cost Appraisal respectively. |
Incremental assessment considers the full assessment profile The three-part rating for an activity, rated as high, medium or low e.g. HMM, and representing the assessment for Strategic Fit, Effectiveness, and Benefit and Cost Appraisal respectively. as follows:
The NZ Transport Agency’s assessment framework is to be used to determine incremental assessment profiles. |
NZ Transport Agency requirement |
The NZ Transport Agency requires incremental assessment to be applied to all investment decisions involving option selection or changes to endorsed macroscopes for any activity where funding is being sought or has been approved from the National Land Transport Fund. |
When to apply incremental assessment |
Incremental assessment is expected to be applied in the following situations:
|
Where incremental assessment is not applicable |
Incremental assessment is not applicable where the options are not mutually exclusive, e.g. attempting to decide between projects within a package, where all projects within the package are critical to its performance and synergistic benefits exist between the projects. |
General methodology |
The following provides a general methodology to apply in cases of option selection and scope changes. There are some variations required to cover specific situations, as discussed in the following sections.
The general assessment methodology is:
|
Project An activity that has a defined start, end and scope. Also see capital project. option selection – variations to general methodology |
For improvement project options, incremental assessment is required to select the preferred option from a short list of options. Short-listing may involve a sieving process to score long-list options against relevant criteria, which should always include economic efficiency at a minimum as a value for money Selecting the right things to do, implementing them in the right way, at the right time and for the right price. factors.
The incremental assessment for strategic fit, effectiveness and economic efficiency follows the general methodology above.
For the incremental profile comparison:
|
Package/plan optimisation – variations to general methodology |
Incremental assessment should be used to optimise packages and implementation plans. Optimising packages and implementation plans includes consideration of project/element timing and sequencing within operational and funding constraints.
The assessment methodology requires a first step of developing mutually exclusive options, which reflect the range of sequencing/timing alternatives A strategic option that may encompass a mix of modes and/or high level routes and/or land use options. Alternatives would be considered during strategy development, with the preferred alternative being selected and taken through into package and project development. available within realistic operational and funding scenarios.
The incremental assessment for strategic fit, effectiveness and economic efficiency follows the general methodology above.
For the incremental profile comparison:
|
Project An activity that has a defined start, end and scope. Also see capital project. / package scope changes – variations to general methodology |
Scope changes proposed to projects and plans following macroscope The information required for the "notice of requirement" under the Resource Management Act 1991, reflecting the scope of the preferred option selected for an improvement project. endorsement must be assessed incrementally. This is regardless of whether the project/package plus the scope changes can be delivered within the approved funding budget. The reason for this is that the funds consumed by the scope change may be released to fund an alternative higher value activity, which means that their allocation to fund the scope change must be justified.
The assessment methodology requires that the project/package with its endorsed macroscope The information required for the "notice of requirement" under the Resource Management Act 1991, reflecting the scope of the preferred option selected for an improvement project. is to be treated as the base case. The scope change is to be treated as an option and incrementally assessed against the base case.
The incremental assessment for strategic fit, effectiveness and economic efficiency follows the general methodology above other than the incremental effectiveness of the scope change being assessed as a higher cost option against the base case. Scope changes may increase or decrease the project/package’s effectiveness and this difference is to be rated in the incremental assessment.
For the incremental profile comparison:
|
Programme Interrelated and complementary combination of activities that, when delivered in a coordinated manner, produce synergies – can span more than one work category and more than one activity class, e.g. a programme could include a road improvement and public transport improvement activities. scope changes – variations to general methodology |
Material scope changes proposed to programmes, e.g. new additional public transport services, need to be assessed incrementally. This is regardless of whether the programme plus the scope changes can be delivered within the approved funding budget. The reason for this is that the funds consumed by the scope change may be released to fund an alternative higher value activity, which means that their application to the scope change must be justified.
The assessment methodology requires that base programme is to be treated as the base case. The scope change is to be treated as an option and incrementally assessed against the base case.
The incremental assessment for strategic fit, effectiveness and economic efficiency follows the general methodology above other than the incremental effectiveness of the scope change being assessed as a higher cost option against the base case. Scope changes may increase or decrease the programme’s effectiveness and this difference is to be rated in the incremental assessment.
For the incremental profile comparison:
|
Last Updated: 04/11/2015 7:58pm
The new look P&I Knowledge Base has been launched on the NZTA website.
Available sections are:
Remaining sections are being updated to reflect the Transport Agency reorganisation and will be available soon.
Don't have an account? Register