Apply for increased programme funding

Introduction

Approved Organisations (AOs) and the NZTA (State Highways) should apply for increased programme funding for additional minor improvements through Transport Investment Online (TIO The NZTA's web-based funding allocation system. ).

 

Process for applying for increased funding

Approved Organisations or the NZTA (State Highways) may apply for increased funding either as a fiscally neutral cash-flow adjustment (bringing funding forward from the next year of the NLTP A National Land Transport Programme Interrelated and complementary combination of activities that, when delivered in a coordinated manner, produce synergies – can span more than one work category and more than one activity class, e.g. a programme could include a road improvement and public transport improvement activities. adopted by the NZTA under section 19 of the LTMA, as from time to time amended or varied ) or as a cost-scope adjustment (increasing their minor improvements allocation for the NLTP as a whole).

 

The application should be made via the Reviews module in TIO The NZTA's web-based funding allocation system. .

 

End-of-year carryovers

Carryover The unexpended allocation for an approved project in any year that is required in the next year. of unspent allocation in the minor improvements work category A type of activity – not confined to a particular activity class, e.g. new roads (work category 323) appears in:

* activity class 12 – local road improvements
* activity class 13 – state highways improvements
will only be considered in exceptional circumstances and only within the 3 years NLTP A National Land Transport Programme Interrelated and complementary combination of activities that, when delivered in a coordinated manner, produce synergies – can span more than one work category and more than one activity class, e.g. a programme could include a road improvement and public transport improvement activities. adopted by the NZTA under section 19 of the LTMA, as from time to time amended or varied

 

The application should be made via the Reviews module in TIO The NZTA's web-based funding allocation system. and must include justification as to why the funds should be carried forward.  Approval will be made by the NZTA Board The NZ Transport Agency Board. or approved delegate.

 