Introduction |
This page relates to the 2012-15 NLTP A National Land Transport Programme Interrelated and complementary combination of activities that, when delivered in a coordinated manner, produce synergies – can span more than one work category and more than one activity class, e.g. a programme could include a road improvement and public transport improvement activities. adopted by the NZTA under section 19 of the LTMA, as from time to time amended or varied only.
For the latest information, please see the Assessment Framework for the 2015-18 NLTP.
This section sets out the factors that must be taken into account, at a minimum, when undertaking a peer review of improvement projects. The peer review must include at least a review of the:
|
Selection and independence of peer reviewer |
The NZ Transport Agency requires an independent, external peer review for any large (over $5million construction cost) or complex project A project with a construction/implementation cost estimate greater than $20 million and/or considered to be high risk. . Approved Organisations and the NZTA (state highways) are encouraged to have small projects (between $250,000 and $5million construction cost) externally peer reviewed if the cost and/or benefit risks associated with these are considered high or the applicant lacks experience in the development and implementation of such projects. In any event, all small project An improvement project with a construction/ implementation cost of $5 million or less and more than $300,000. evaluations should be internally peer reviewed.
Where an external peer review is required or warranted, the peer reviewer shall be selected and appointed by the applicant, and must:
For very large, complex packages and projects, a peer review panel, covering a range of competencies, may be most appropriate.
The NZ Transport Agency reserves the right to undertake its own peer review of any project or to require the Approved Organisation or the NZTA (state highway) to appoint a specific peer reviewer or to establish a peer review panel with appropriate competencies. |
Conformity |
The reviewer must first determine whether the project is eligible for funding in that it fits the description of one of the activity classes in the current Government Policy Statement on Land Transport Funding.
The reviewer must ensure that the project evaluation conforms to the requirements of this Knowledge Base, including that it has been assessed by the applicant in conformance with the NZ Transport Agency’s Assessment Framework. |
Credibility |
To check credibility, the reviewer must:
|
Choice of do minimum |
The reviewer must assess the do-minimum as stated in the project report and must determine whether it is realistic, and does not represent another option to be considered in the analysis. |
Identification and selection of alternatives A strategic option that may encompass a mix of modes and/or high level routes and/or land use options. Alternatives would be considered during strategy development, with the preferred alternative being selected and taken through into package and project development. and options |
The reviewer must examine the evaluation and judge whether all feasible alternatives A strategic option that may encompass a mix of modes and/or high level routes and/or land use options. Alternatives would be considered during strategy development, with the preferred alternative being selected and taken through into package and project development. and options have been identified and considered adequately. These should include alternative transport modes, where applicable, and low cost options.
The reviewer needs to be satisfied that the process to select the preferred alternative and option(s) has been robust and includes incremental assessment where appropriate. |
Strategic fit rating |
The reviewer needs to be satisfied that the strategic fit rating for the activity is correct. |
Effectiveness rating |
The reviewer needs to be satisfied that the effectiveness rating for the activity is correct. |
Cost estimate |
The reviewer shall check compliance with parallel cost estimate process requirements, where applicable. |
Economic efficiency evaluation and rating |
The reviewer must determine whether the economic efficiency evaluation has conformed to all the relevant requirements of the NZ Transport Agency’s Economic Evaluation Manual (Jan 2016). The reviewer must determine whether there are any outstanding issues not addressed in the project report.
If there is a departure from the requirements, or any defect or omission, the reviewer must comment on its significance.
Where the reviewer considers that there have been discrepancies and departures from procedure, or has concerns on cost and/or benefit estimation, the reviewer will determine the project benefit cost ratio (BCR The NZTA uses the BCR as a measure of economic efficiency from a national perspective as defined in the NZTA's Economic Evaluation Manual. The ratio compares the benefits accruing to land transport users and the wider community from implementing a project or providing a service, with that project or service's whole of life costs. ) and compare this with the applicant’s calculations.
The reviewer must determine whether the options identified in the analysis are mutually exclusive options of the same project. If the options identified:
In special cases, other economic impacts may be considered (e.g. intangibles). These are to be shown as sensitivity analyses, in addition to the EEM The NZTA's Economic evaluation manual. procedure economic analysis.
Where supplementary (third party) funding is involved, a government BCR The NZTA uses the BCR as a measure of economic efficiency from a national perspective as defined in the NZTA's Economic Evaluation Manual. The ratio compares the benefits accruing to land transport users and the wider community from implementing a project or providing a service, with that project or service's whole of life costs. must be determined in addition to the national BCR. |
Risk assessment, analysis and mitigation |
The reviewer must ensure that:
|
Sensitivity analysis |
The reviewer must consider whether the sensitivity of critical aspects of the project evaluation has been covered off adequately, paying particular attention to:
|
Raising concerns |
The reviewer must raise in writing with the applicant organisation for funding assistance (and its representative) any:
The reviewer must request that the applicant organisation:
The review must note any outstanding concerns in the review report. |
Last Updated: 22/02/2017 9:05am
The new look P&I Knowledge Base has been launched on the NZTA website.
Available sections are:
Remaining sections are being updated to reflect the Transport Agency reorganisation and will be available soon.
Don't have an account? Register